Resurfacing In Olympia

The week of July 22, 2013, the City’s Contractor will be preparing the following roads for resurfacing:

Plum Street (from Union Avenue to Olympia Avenue);

Lybarger Street (from Prospect Avenue to Glass Avenue); 

Glass Avenue (from Central Street to Fir Street).

Resurfacing work will occur on July 27th, July 28th, August 3rd, and August 4th between 7:00 a.m. and 6:00 p.m.

Traffic Impacts At least one lane of traffic will be open during construction. Traffic control and flaggers will be in place, so please use caution when traveling through the area. Travelers may experience delays, and are asked to consider using alternate routes. No “on-street” parking will be available. Vehicles parked on the shoulder during paving operations are subject to towing.

Get real-time project updates: OLY PROJECTS/TWITTER